Builder Directed to Hand Over Flat with OC Within Two Months; Maharashtra Consumer Commission Awards 9% Interest and ₹2.5 Lakh Compensation
By Adv. Sulaiman Bhimani
The State Consumer Disputes Redressal Commission, Maharashtra has held that accepting more than 10% of the apartment cost without executing and registering an Agreement for Sale violates Section 13 of the Real Estate (Regulation and Development) Act, 2016 and constitutes deficiency in service and unfair trade practice under the Consumer Protection Act, 2019.
A Bench comprising President in Charge Mukesh V. Sharma and Member Poonam V. Maharshi partly allowed a consumer complaint filed by Mumbai residents Mrs. Sumana Panja and Mr. Bhavesh Manu Macwana against Goregaon-based developer M/s. Raj Builders & Developers. The Commission directed the builder to hand over vacant and peaceful possession of Flat No. 1803 in the project “Raj Pantheon” at Goregaon (West) along with the Occupation Certificate within two months.
The Commission further ordered the developer to pay interest at 9% per annum on the paid consideration from January 1, 2023 until actual possession is delivered, alongside Rs. 2,00,000 towards compensation for mental agony and harassment and Rs. 50,000 towards litigation costs.
Also Read RERA: Builders cannot hide under force majeure to deny interest for delayed possession
Case Background and Factual Matrix
In October 2018, Complainant No. 2 and his mother booked Flat No. A-1901 on the 19th floor of “Goregaon New Subhash Nagar CHSL” in the “Raj Pantheon” project for a total consideration of Rs. 73,00,000, inclusive of taxes and duties. The developer committed to completing construction and obtaining the Occupation Certificate on or before December 31, 2021.
Between October 2018 and October 2019, the buyers paid Rs. 14,78,000, exceeding 20% of the total consideration, without any payment default. Despite repeated follow-ups, the developer did not execute or register an Agreement for Sale for over three years.
Following Complainant No. 2’s marriage in May 2021, the parties agreed to substitute his wife, Complainant No. 1, as co-purchaser in place of his mother, and shifted the allotment to Flat No. 1803 on the 18th floor for a revised total consideration of Rs. 71,58,000.
Disputed Interest Demands and Unilateral Extension
After the original December 2021 deadline lapsed, the developer issued demand letters in December 2021 and January 2022 seeking Rs. 10,81,508 towards interest at 21% per annum for alleged payment defaults. The buyers contested these demands, pointing out that no demand had been raised since October 2019 and no registered Agreement for Sale existed as mandated under Section 13 of RERA.
The developer admitted the demands were faulty and withdrew them. On March 15, 2022, a registered Agreement for Sale for Flat No. 1803 was executed for Rs. 71,58,000, incorporating a unilaterally extended possession date of December 31, 2022. The buyers availed a home loan from HDFC Bank Ltd. and paid Rs. 64,80,988, representing approximately 90.5% of the total consideration, leaving a balance of roughly Rs. 6,77,012.
Even after the extended December 2022 deadline passed, the developer failed to deliver possession qa withdrawn 21% interest claims. The buyers also lodged a police complaint at Goregaon Police Station in April 2023 alleging cheating, criminal breach of trust, and criminal intimidation. Meanwhile, the developer’s last MahaRERA project extension expired on June 30, 2024 without possession being handed over.
Read Also Bombay High Court Directs Execution of MahaRERA Recovery Warrants Within Eight Weeks: What Homebuyers Should Know
Findings of the State Commission
Despite due service of notice in November 2024, the developer failed to appear or file a written statement, leading the Commission to proceed ex-parte on July 17, 2025.
Examining the unrebutted documentary record, the Commission held that the complainants qualified as consumers under Section 2(7) of the Consumer Protection Act, 2019, and that the complaint was within limitation under Section 69 due to the continuing cause of action arising from non-delivery of possession.
On merits, the Bench observed that collecting over 20% of the consideration between 2018 and 2019 without registering an Agreement for Sale until March 2022 directly contravened Section 13 of RERA. Holding that inordinate delay and unilateral extension of possession dates amount to deficiency in service under Section 2(11) and unfair trade practice under Section 2(47) of the Consumer Protection Act, 2019, the Commission relied on Supreme Court precedents in Wg. Cdr. Arifur Rahman Khan v. DLF Southern Homes Pvt. Ltd. (2020), Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan (2019), and Experion Developers Pvt. Ltd. v. Sushma Ashok Shiroor (2022).
The Bench further ruled that the builder could not revive the faulty 21% interest demands that it had already withdrawn and omitted from the registered agreement.
Also Read Maharashtra Consumer Commission Rejects Nahar Builders’ 441-Day Delay Plea in Bandra Conveyance and Leasehold Dispute
Media Coverage: Free Press Journal Reports on the Landmark Consumer Ruling
The ruling has also received coverage in The Free Press Journal, Mumbai edition, dated 26 November 2026, under the headline “Homebuyers Win Possession, 9% Interest”. The report, authored by Pranali Lotlikar, highlights the Maharashtra State Consumer Disputes Redressal Commission’s directions requiring Raj Builders & Developers to hand over possession of the flat along with the Occupation Certificate within two months, pay interest at 9% per annum on the amount paid by the homebuyers, and provide compensation for mental agony and litigation costs.
The newspaper coverage brings wider attention to the consumer rights issues arising from delayed possession of residential properties and the accountability of real estate developers under the consumer protection framework.
Final Directions
Partly allowing Consumer Complaint No. CC/140/2024, the Maharashtra State Consumer Commission directed M/s. Raj Builders & Developers to hand over vacant and peaceful possession of Flat No. 1803, admeasuring 351 sq. ft. carpet area, with the Occupation Certificate within two months, upon the buyers paying the legitimate balance consideration as per the March 15, 2022 agreement.
The developer must also pay delay interest at 9% per annum on the paid amount from January 1, 2023 until actual possession, Rs. 2,00,000 for mental agony, and Rs. 50,000 towards litigation costs.
Also Read Builder Cannot Hand Over Possession Without Occupation Certificate
Case Details
Case Title: Mrs. Sumana Panja and Anr. v. M/s. Raj Builders & Developers Case Number: Consumer Complaint No. SC/27/CC/24/140 Coram: Hon’ble Mr. Mukesh V. Sharma (President in Charge) and Hon’ble Ms. Poonam V. Maharshi (Member) Date of Judgment: August 31, 2026 Counsel for Complainants: Advocate Bhimani, instructed by The Law Suits Counsel for Opposite Party: Ex-parte
Disclaimer: This report is strictly for informational and academic awareness regarding judicial orders and does not constitute legal advice or solicitation of legal work in accordance with Rule 36 of the Bar Council of India Rules.
Click Here to Read and Download The Order
The Law Suits
Advocates & Legal Consultants
413, Golden Chambers, Opposite Tanishq Showroom,
Near Lower Oshiwara Metro Station (Landmark: Citi Mall),
New Link Road, Andheri (West), Mumbai – 400053
Call +91 8928372392
Website: www.thelawsuits.in
Website: www.thelawsuits.in